Location Confidential
A desulphurisation plant to an existing power station (gas and natural fossil fuel), comprising all mechanical and electrical engineering installations, power and power distribution, operations instrumentation and control systems together with all associated building and civil works. Our Client was one of the tenderers selected by the local government agency for power (the Employer) for final negotiations of an agreed contract.
KEY FEATURES
The contract was to be awarded on a fixed-price, lump-sum,
turnkey basis using the Employer’s standard form of
design and build contract. The contract programme required
our Client in erecting, installing, commissioning and testing
the entire desulphurisation plant during the period when
the power station was operational and without interruption
to power supplies. This involved numerous complex technical
and resultant contractual interfaces. In addition, the form
of contract and the general conditions posed a number of
exceptionally high levels commercial risk in the opinion
of our client and provisions for such eventualities had
to be made without jeopardizing the negotiations towards
a successful bid.
CONSULTANCY SERVICES – Commercial
and Contractual Risk Analysis
Lancaster House International Consulting were requested
by our Client to undertake a commercial and contractual risk
analysis in respect of the “Head Contract", to
identify and highlight categories and areas of risk with a
prognosis of potentiality and “what if” scenarios.
Simultaneously, we were required to draft provisions under
a set of “Special Conditions of Contract” for
negotiation with the Employer as considered necessary, in
our opinion, to mitigate and otherwise mange the said risks
together with providing our Comments & Recommendations
on risk pricing and risk management . The initial contract
appraisal and risk analysis comprised a detailed examination
of the Instructions to Tenderers, other bid documentation
issued by the Employer, the General Terms and Conditions of
Contract, specifications and drawings. We looked into risk
types emanating from technical, commercial and contractual
sources and from this, we identified, for example, several
major potential commercial risk items through important omissions
within contractual terms and conditions. Certain provisions
as drafted in the tender documents were wholly inappropriate
to the nature of the project and the objectives of both the
Employer and Contractor. Examples of such poor drafting were
the limiting effect upon the Employer’s rights to issue
variation orders, the Contractor’s entitlement to obtain
an extension of time for delay, and the reimbursement of prolongation
costs and other additional costs arising therefrom. A detailed
subject matrix of risk exposure under the provisions of the
Head Contract was also drafted with corresponding recommendations.
In order to classify the seriousness of the risk a simple classification by categories was adopted namely:-
Category 1: Serious Risks (A - Technical
/ B - Commercial / C - Contractual)
Strenuous efforts to achieve acceptance of suitably amended
wording of the offending article, clause, provision to eliminate
the risk(s) in entirety.
Category 2: Significant Risk (A - Technical
/ B - Commercial / C - Contractual)
Conditions of Contract wording to be amended if possible
during negotiation (through clarifications and qualifications)
and where possible transferred to the Employer or others.
Otherwise, such risks to be monitored and managed.
Category 3: Allowable Risk to be allowed for (priced) within the Tender Submission.
Category 4: Low Risk Issues to be monitored and controlled
Special Conditions of Contract were drafted by us to eliminate the identified Serious Risks and we were successful in assisting our Client in negotiating with the Employer to obtain the entire elimination or transfer of such risks to the Employer.
Finally, Lancaster House International Consulting provided further recommendations to minimise the risk by way of effective documentation and tracking of same, project records, the early identification of entitlement, and prompt notification, including close relations between technical / commercial / contractual corporate divisions and the rapid conversion of entitlement into quantified and reimbursed claims.